Readiness Criteria

The detailed Project Cost Estimate Table

Component, activity and sub activity wise cost estimate table

Click here to download Example Project cost tab - Gujarat Version (10th May 2016)

The Detailed Project Implementation Plan (PIP) Report Project (NHP) - central as well as states

The Detailed Project Implementation Plan (PIP) Report is a pre-requisite document that needs to be prepared by all the implementing agencies of the National Hydrology Project (NHP) - central as well as states.

Click here for Revised Project Implementation Plan

Overview on National Hydrology Project preparation guidance

This will provides a guideline to all implementing agencies on the necessary steps to be taken in the preparation of the National Hydrology Project (NHP). The subsequent sections include step-by-step instructions, templates, sample documents and reference materials to enable implementing agencies to 1) To prepare a detailed action plan 2) To quantify baseline and proposed requirements that are necessary for setting the indicators of the project.All agencies are requested to review each section thoroughly before submitting the required documents.

Please contact us if you have any queries/suggestions/feedback

Readiness Criteria

The Department of Economic Affairs (DEA) has set stringent readiness criteria for making the National Hydrology Project (NHP) effective. To meet the readiness criteria, the following actions require immediate attention by all NHP implementing agencies (central and state): (1) Setting up of a Project Management Unit (2) Preparation of a Work-Plan for Year 1 and Year 2 (3) Preparation of a Procurement Plan for the first 18 months. The above mentioned documents need to be submitted to the Ministry of Water Resources (DoWR), RD & GR via the existing Management Information System (MIS) before 30th July 2016.

Link to Management information system for uploading the documents and online filling the project implementation plan

Preparation of a Work-Plan for Year 1 and Year 2

Work Plan is an outline of phasing project activities to be carried out in a financial year including its physical and financial aspects

Click here to download Annual Work Plan Format.

Preparation of a Procurement Plan for the first 18 months

Procurement Plan detailing out procurement activities envisaged to be carried out during a financial year including its financial aspects

Click here to Download Procurement Plan Format.